Comments on the 2024 Environmental Agreement Annual Report, Ekati Diamond Mine (Independent Environmental Monitoring Agency, July 2025)
The Independent Environmental Monitoring Agency reviews the 2024 Ekati Diamond Mine Environmental Agreement Annual Report and finds it satisfactory but the Summary Report unsatisfactory, identifying four key deficiencies: omission of water licence exceedances, insufficient detail on elevated mercury and selenium in fish tissues, missing acid deposition and incinerator stack testing results, and discrepancies in King Pond discharge dates.
- Date
- 2025-07-18
- Document type
- letter
- Parties
- Independent Environmental Monitoring Agency, Laurie McGregor, GNWT - Environment and Climate Change, Burgundy Diamond Mines Ltd., Tłı̨cho Government, Yellowknives Dene First Nation, Łutsel K'e Dene First Nation, North Slave Metis Alliance, Kitikmeot Inuit Association, Government of the Northwest Territories, Crown-Indigenous Relations and Northern Affairs Canada
- Locations
- Ekati Diamond Mine, Yellowknife, Northwest Territories, King Pond Settling Facility, Cujo Lake, Koala watershed
- Parameters
- water quality, effluent quality criteria, total aluminum, sulphate, pH, TSS, arsenic, selenium, iron, potassium, aquatic effects monitoring, mercury in fish tissue, selenium in fish tissue, acid deposition, air quality monitoring, greenhouse gas emissions, dustfall, incinerator stack testing, dioxins and furans, compliance