East Desperation Pond Cofferdam As-Built Construction Report, Ekati Diamond Mine (EBA Engineering, July 2002)
East Desperation Pond Cofferdam As-Built Construction Report for the Ekati Diamond Mine (BHP Billiton Diamonds Inc., Project No. 0101-94-11580.058), July 2002, prepared by EBA Engineering Consultants Ltd. Includes the As-Built Construction Drawings package (Drawing Index: 11580.058-DPAB01 General Location and Misery Site Plan), UTM Coordinates (NAD 83), East Cofferdam construction sequence (GCL Liner placement at elevations 5.10 / 2.95 / 2.15 / 0.75 m), and loading-ramp configuration for front-end-loader external-feed hopper with Grizzly conveyor.
- Date
- 2002
- Document type
- report
- Parties
- BHP Billiton Diamonds Inc., EBA Engineering Consultants Ltd., Melody Macleod, Mackenzie Valley Land and Water Board, MVLWB
- Locations
- Yellowknife, Northwest Territories
- Parameters
- cofferdam, as-built construction, desperation pond, water licence N7L2-1616, waste rock dam, ekati diamond mine
- Pages
- 66