Environmental Assessment (EA) Information Update #1, BHP Ekati Diamond Mines Expansion (MVEIRB, September 1999)
The Mackenzie Valley Environmental Impact Review Board distributes a regular update on environmental review activities for the BHP Ekati diamond mine expansion and the Ranger Oil/Canadian Forest Oil/Chevron natural gas development, outlining required consultations, development descriptions, and next steps in the environmental assessment process.
- Date
- 1999-09-20
- Document type
- memo
- Parties
- Mackenzie Valley Environmental Impact Review Board, BHP, Ranger Oil Ltd., Canadian Forest Oil, Chevron Canada Resources, Roland Samjanovs, Heidi Klein, Bridgette Larocque, Gordon Stewart, Louie Azzolini
- Locations
- Ekati, Lac de Gras, Fort Liard, Fort Simpson, Mackenzie Valley
- Parameters
- Sable kimberlite pipe, Pigeon kimberlite pipe, Beartooth kimberlite pipe, environmental assessment, mine expansion
- Pages
- 1
Original document