Skip to content
AI-generated answers are sourced from this archive. Verify against the linked source documents.

Project Descriptions, Ekati Diamond Mine (BHP Billiton, 1998 to 2001)

EBA Engineering's final design report for the Long Lake intermediate dykes at Ekati Diamond Mine, detailing the engineering design, site geotechnical conditions, stability analyses, and construction specifications for four rockfill retention dykes to subdivide the tailings basin into five cells.

Date
Document type
Report
Parties
BHP Diamonds Inc., EBA Engineering Consultants Ltd.
Locations
Ekati Diamond Mine, Long Lake, Lac de Gras, Northwest Territories, Yellowknife
Parameters
tailings retention, dam design, slope stability, foundation conditions, filter testing, water quality, permafrost, rockfill dykes
Pages
117

Original document

Loading the document…