Sedimentation Ponds Preliminary Design, NWT Diamonds Project (EBA Engineering, December 1995)

This preliminary design report documents the planned sedimentation pond systems for four kimberlite pit mines (Panda/Koala, Misery, Fox, and Leslie) at the NWT Diamonds Project. The ponds are designed to impound turbid water and soft lake sediments from pit dewatering and to provide settling basins during mine operation, with specific designs for valley ponds and lake basin ponds incorporating pervious dikes, impervious dams, and frozen core structures adapted to permafrost conditions.

Date
1995
Document type
Report
Parties
BHP Diamonds Inc., EBA Engineering Consultants Ltd., Golder Associates, Rescan
Locations
NWT Diamonds Project, Northwest Territories, Panda Lake, Koala Lake, Misery Lake, Fox Lake, Leslie Lake, Nero Lake, Long Lake, Vancouver, BC, Edmonton, Alberta
Parameters
sedimentation ponds, water quality, suspended solids, turbidity, smectitic clay minerals, pit dewatering, sediment characterization, water and material balance, dike design, dam design, seepage analysis, consolidation, filtration, flocculants, discharge criteria, permafrost, thermal analysis, erosion control
Pages
35